Connect Control Wiring
Route 24v control wires through control wiring grommet and connect leads to control wiring. See Thermostat Installation Instructions for wiring specific unit combinations. (See Fig. 9.)
Use No. 18 AWG
All wiring must be NEC Class 1 and must be separated from incoming power leads.
Use furnace transformer, fan coil transformer, or accessory transformer for control power, 24v/40va minimum.
NOTE: Use of available 24v accessories may exceed the minimum 40va power requirement. Determine total transformer loading and increase the transformer capacity or split the load with an accessory transformer as required.
Final Wiring Check
IMPORTANT: Check factory wiring and field wire connections to ensure terminations are secured properly. Check wire routing to ensure wires are not in contact with tubing, sheet metal, etc.
STEP 9 —Compressor Crankcase Heater
When equipped with a crankcase heater, furnish power to heater a minimum of 24 hr before starting unit. To furnish power to heater only, set thermostat to OFF and close electrical disconnect to outdoor unit.
A crankcase heater is required if refrigerant tubing is longer than
80ft. Refer to the Long Line
STEP 10
Refer to the individual instructions packaged with kits or accessories when installing.
STEP 11
!CAUTION
PERSONAL INJURY HAZARD
Failure to follow this caution may result in personal injury.
Wear safety glasses, protective clothing, and gloves when handling refrigerant and observe the following:
S Front seating service valves are equipped with Schrader valves.
!CAUTION
ENVIRONMENTAL HAZARD
Failure to follow this caution may result in environmental damage.
Federal regulations require that you do not vent refrigerant to the atmosphere. Recover during system repair or final unit disposal.
!CAUTION
UNIT OPERATION AND SAFETY HAZARD
Failure to follow this caution may result in minor personal injury, equipment damage or improper operation.
To prevent compressor damage or personal injury, observe the following:
S Do not overcharge system with refrigerant.
S Do not operate unit in a vacuum or at negative pressure. S Do not disable low pressure switch in scroll compressor
applications.
S Dome temperatures may be hot.
Follow these steps to properly start up system:
1.After system is evacuated, fully open liquid and vapor service valves.
2.Unit is shipped with valve stem(s) front seated (closed) and caps installed. Replace stem caps after system is opened to refrigerant flow (back seated). Replace caps
3.Close electrical disconnects to energize system.
4.Set room thermostat at desired temperature. Be sure set point is below indoor ambient temperature.
5.Set room thermostat to HEAT or COOL and fan control to ON or AUTO mode, as desired. Operate unit for 15 minutes. Check system refrigerant charge.
25HCR