![Step 7 — Make Electrical Connections — All](/images/new-backgrounds/69840/6984027x1.webp)
SYSTEM
DILUTED
POT FEEDER AND TRANSFER PUMP
Step 7 — Make Electrical Connections — All
field wiring must comply with local code requirements. Electrical data for the complete unit and for the compressors is shown in Table 3. See Fig. 16 for field wiring connections. A
CLEANING
AGENT
|
|
|
|
|
|
|
| x |
|
|
|
|
|
|
|
|
|
| |
|
|
|
|
|
|
|
|
| |
|
|
|
|
|
|
|
|
|
|
| TEMPORARY |
| 30MPUNIT | ||||||
| PUMP |
|
| ||||||
|
|
|
|
|
|
|
| x |
|
|
|
|
|
|
|
|
|
| |
|
|
|
|
|
|
| |||
|
| TEMPORARY | |||||||
| |||||||||
|
| TO DRAIN | BYPASS | ||||||
|
|
|
|
Fig. 14 — Typical Set Up for Cleaning Process
SYSTEM
Control circuit power is 24 v on all units.
Inside the control box are terminals for field power and ground (earth) wiring. A ground wire must be installed with each field power supply. Compressors are wired for
FLOW SWITCH — A condenser flow switch is available as an accessory for all 30MPW units, and can be
DILUTED
POT FEEDER AND TRANSFER PUMP
located in the field wiring compartment of the control box. The flow switch should be wired between terminals
SIDE
STREAM FILTER
CLEANING
AGENT
| x |
TEMPORARY | 30MPUNIT |
PUMP |
|
x
CONTROL BOX, POWER SECTION — The electrical power supply is brought in through the top
The control box power section contains the following
|
| TEMPORARY |
| ||
|
| BYPASS |
| TO DRAIN |
Fig. 15 — Cleaning Using a Side Stream Filter
Ensure the following when filling the system:
1.Remove temporary bypass piping and cleaning/flushing equipment.
2.Check to make sure all drain plugs are installed.
3.Open the
Normally, a closed system needs to be filled only once. The actual filling process is generally a fairly simple procedure. All air should be purged or vented from the system. Thorough venting at the high points and circulation at room temperature for several hours is recommended.
NOTE: Local codes concerning backflow devices and other protection of the city water system should be consulted and followed to prevent contamination of the public water supply. This is especially important when antifreeze is used in the system.
Set Water Flow Rate — Once the system is cleaned, pressur- ized, and filled, the flow rate through the chiller needs to be established.
NOTE: Carrier recommends a differential pressure gage when measuring pressures across the pumps or balancing valves. This provides for greater accuracy and reduces error
On primary/secondary systems, it is advisable to set the 30MP balancing valve to maintain design flow plus 10% through the chiller.
A rough estimate of water flow can also be obtained from measuring the pressure drop across the 30MP heat exchanger. Figures 11 and 12 show the relationship between gpm and heat exchanger pressure drop. It should be noted that these curves are for “clean” heat exchangers; they do not apply to heat ex- changers with fouling. Adjust the external balancing valve until the correct pressure drop is obtained for the required gpm.
components:
•power terminal block
•optional disconnect switch
•compressor circuit breaker(s)
•compressor contactor(s)
•current sensor boards
•control transformer
•ground lug
•neutral terminal
•crankcase heater relay (30MPA units only)
•fuses
CONTROL BOX, CONTROLS SECTION — The control box controls section contains the following components:
•main base board (MBB)
•scrolling marquee display
•optional energy management module
•
•
•unit Enable/Off/Remote contact switch
•unit Alarm/Alert indicator light
CONTROL BOX, FIELD CONTROL WIRING SEC- TION — Inside this section is the
The unit has the capability to control
UNBALANCED
% Voltage Imbalance =
100 x | max voltage deviation from average voltage | |
average voltage | ||
|
14