NOTES:
1.Chiller must be installed level to maintain proper compressor oil return.
2.Wiring and piping shown are general
3.All wiring must comply with applicable local and national codes.
4.All piping must follow standard piping techniques. Refer to Carrier System Design Manual part 3, Carrier
5.See Tables 1A and 1B for minimum system fluid volume. This sys- tem may require the addition of a holding tank to ensure adequate volume.
6.Hot gas lines should rise above refrigerant level in condenser cir- cuit. Double riser may be required; check unit minimum capacity.
7.Trap should be installed on hot gas lines to prevent condenser oil
and refrigerant vapor migration from accumulating in compressor during off cycle.
8. Pitch all horizontal lines downward in the direction of refrigerant flow.
9.Provide support to liquid and gas lines near the connections to the condenser coil.
10.For pressure relief requirements, see latest revision of ASHRAE Standard 15, Safety Code for Mechanical Refrigeration.
11.A strainer with a minimum of 40 mesh must be installed within 10 ft (3 m) of the evaporator fluid inlet to prevent debris from clogging or damaging the heat exchanger. This strainer is required and is avail- able as an accessory.
12.Piping, wiring, switches, vents, strainers, drains, and vibration iso- lation are all
Fig. 9 — Typical Piping with 30MPA Unit and 09DP Remote