USING FLEXIBLE VENT COMPONENTS
FIGURE 19

14

USING FLEXIBLE VENT COMPONENTS

Use only approved aluminum flexible liner kits marked:

"Wolf Steel Approved Venting" as identified by the stamp only on the 8” outer liner.

For safe and proper operation of the fireplace, follow the venting instructions exactly.

HORIZONTAL AIR TERMINAL INSTALLATION

A VENT HEAT SHIELD MUST BE USED IF THE WALL TERMI- NAL IS INSTALLED ON COMBUSTIBLE, EXTERIOR SUR- FACES.

1.Cut or frame a hole in an exterior wall with a minimum round or square opening of 10½ inches. Secure the firestop spacer over the opening to the interior wall.

2.Stretch the 5" diameter aluminum flexible liner to the required length taking into account the additional length needed for the finished wall surface. Slip the liner a mini- mum of 2" over the inner sleeve of the air terminal and secure with 3 #8 screws. Apply a heavy bead of the high temperature sealant.

3.Using the 8" diameter flexible aluminum liner, slide over the outer combustion air sleeve of the air terminal and secure with 3 #8 screws. Seal as before.

FIGURE 18

The air terminal mounting plate may be recessed into the exterior wall or siding by 1½", the depth of the return flange.

4.Insert the liners through the firestop maintaining the required clearance to combustibles. Holding the air termi- nal (lettering in an upright, readable position), secure to the exterior wall and make weather tight by sealing with caulking (not supplied).

5.Apply a heavy bead of the high temperature sealant, supplied with the unit, to the inside of the 5" liner approxi- mately 1" from the end. Slip the liner a minimum of 2" over the fireplace vent collar and secure with 3 #8 screws.

6.Using the 8" diameter flexible aluminium liner, apply sealant, slide a minimum of 2" over the fireplace combus- tion air collar and secure with 3 #8 screws.

7.If more liner needs to be used to reach the fireplace, couple them together as illustrated. The vent system must be supported approximately every 3 feet for both vertical and horizontal runs. Use noncombustible strapping to maintain the minimum 1" clearance to combustibles.

8.The vent heat shield

must be installed only FIGURE 20 when terminating hori-

zontally with no vertical rise. Remove the two screws nearest the vent collars on the top of the fireplace. Align the vent heat shield (supplied) and secure.See figure 37.

VERTICAL AIR TERMINAL INSTALLATION

FIGURE 21

1. Fasten the roof support to the roof using the screws provided. The roof support is optional. In this case the venting is to be

adequately supported us-

ing either an alternate method suitable to the au-

thority having jurisdiction or the optional roof support.

2.Stretch the 5" diameter aluminium flexible liner to the required length. Slip the liner a minimum of 2" over the inner sleeve of the air terminal and secure with 3 #8 screws. Seal using a heavy bead of the high temperature sealant.

3.Repeat using 8" diameter

aluminium flexible liner.

FIGURE 22

4.Thread the air terminal pipe assembly down through the roof. The air terminal must be located vertically and plumb. Attach the air terminal assembly to the roof support, ensuring that a mini-

mum 16" of air terminal will pen- etrate the roof when fastened.

DO NOT CLAMP THE FLEXIBLE

ALUMINIUM LINER.

W415-0385 / A / 10.02.03

Page 14
Image 14
Continental BCDV42P, BCDV42N manual Using Flexible Vent Components, Use only approved aluminum flexible liner kits marked