Enviro EF3 owner manual Installation, is the recommended installation set up

Models: EF3

1 43
Download 43 pages 19.26 Kb
Page 21
Image 21
Figure 25 is the recommended installation set up.

Installation

10.The pipe must extend at least 12” (30 cm) away from the building. If necessary, bring another length of pipe (PL type) to the outside of the home to connect to the first section. Do not forget to place high temperature silicone around the pipe that passes through the thimble.

11.Install a vertical pipe, or if all requirements for direct venting are met, install vent termination. The stainless steel cap termination manufactured by the vent manufacturer is recommended. However, when the vent terminates several feet above ground level and there are no trees, plants, etc. within several feet, a 45° elbow can be used as termination. The elbow must be turned down to prevent rain from entering.

NOTE:

Some horizontal through wall installations may require a “T” and 3 to 5 feet (91 to 152 cm) of vertical pipe outside the building to help naturally draft in the unit.

This may be required if a proper burn cannot be maintained, after the stove has been tested and the airflow set.

This is due to the back pressure in the exhaust caused by airflow around the structure.

All sections of pipe must have three (3) screws evenly spaced and all horizontal and vertical vent sections located within the house must have a bead of high temperature silicone installed on the male end of the pipe before installation to create a gas tight seal.

THROUGH WALL WITH VERTICAL RISE AND HORIZONTAL TERMINATION INSTALLATION - FREESTANDING:

A 45° elbow with a rodent screen may be used in place of the termination cap (or stainless steel termination hood).

Figure 25 is the recommended installation set up.

Figure 26 is the installation to use if there is a concrete or retaining wall in line with exhaust vent on a pellet stove. The termination must be 12” (30 cm) from the outside wall and 12” (30 cm) above the ground.

Termination cap

 

90° elbow

 

Wall framing

 

Vertical section

 

of vent pipe

Wall strap

Horizontal frame

 

for thimble

 

 

Clean out tee

 

Wall thimble

ENVIRO EF3

 

Figure 25: Venting horizontally with rise.

Horizontal frame

 

for thimble

Termination cap

Wall thimble

 

90° elbow

 

Wall framing

 

Vertical section

 

of vent pipe

 

 

Concrete Wall

ENVIRO EF3

Clean out tee

Figure 26: Venting with concrete wall behind unit .

21

Page 21
Image 21
Enviro EF3 owner manual Installation, is the recommended installation set up