3 Quick Start

3.1 Unpacking

Unpack the dry-well carefully and inspect it for any damage that may haveoc-
curred during shipment. If there is shipping damage, notify the carrier
immediately.
Verifythat the following components are present:
9011 Dry-well
Power Cord
User's Guide with Report of Calibration
2 inserts
Insert removal tool
RS-232 Cable
9930 Interface-it Software

3.2 Set-up

Place the calibrator on a flat surface with at least 6 inches of free space around
the instrument. Always leaveenough clearance in front of the instrument to al-
low for safe and easy insertion and removalof probes. Plug the power cord into
a grounded mains outlet. Observe that the nominal voltagecorresponds to that
indicated on the calibrator.

3.3 Power

Plug the instrument power cord into a mains outlet of the proper voltage,fre-
quency,and cu rrent capability.Refer to Section 2.1, Specifications, for the
power details.
Turn on the power to the calibrator by toggling both power switches on within
three seconds of each other.The fans should begin blowing air through the in-
strument and both controller displays should illuminate after 3 seconds. After a
brief self-test the controller should begin normal operation. If the unit failsto
operate please check the power connection.
NOTE: If more than three seconds elapse, (Interconnect Link) ap-
pears on the display. Press any front control panel button to eliminate the
message. The hot block serial commands are not available unless
both power switches were turned on within three seconds of each other.
The display shows the well temperature and the well heater brings the tempera-
ture of the well to the set-point temperature.