g
Digital Energy™ GT Series
6.3.2Battery replacement procedure) 1.5kVA 1 Remove front panel
2 Unscrew two bolts of the
3 battery terminal cover and remove it
4 Unplug battery connectors
5 Unscrew five bolts of the
6 battery compartment cover and remove it
7 Unscrew two bolts of battery fixer and remove it
8 Pull out the battery set and renew it
9 Assemble UPS
by reverse procedure.
Fig. 6.2
6.3.3Battery replacement procedure) 3kVA
NOTE: The battery banks should be installed by service personnel.
1Remove front panel
2Unscrew two bolts of the battery compartment
3Remove battery cover
4Unscrew two bolts
5/6 Remove stop holder and battery terminal 7 Grasp the tag to pull out the battery sets.
Be careful, heavy weight! Notice not to let the battery set to drop in accident
7When you see the first warning label, please disconnect all leads
Continue horizontally pulling the battery set 1 until you see the next warning label (See fig.
7a Now you can easily release battery set 1! (Gently lift it up!) Put battery set 1 beside.
7b Continue pulling out battery set 2.
8Unplug all connectors of batteries
9Renew the batteries and
Fig. 6.3
Fig. 6.4
6.4Recycling the UPS at the end of service life
GE Digital Energy, in compliance with environment protection recommends that the UPS equipment, at the end of its service life, must be recycled conforming to the local applicable regulations.
OPM_GTU_19X_1K0_3K0_XUS_V014 | 18 |