After the engine has completed its cool down cycle and shut down, shut OFF utility power again.

After the engine has completed its cool down cycle and shut down, shut OFF utility power again.

When the generator is supplying power to the transfer switch, move the breakers in the switch to the ON position one at a time until the generator has accepted the entire emergency load.

With the generator carrying the entire emergency load, re-check gas pressure to verify that it

is at the same level it was before you started the generator.

Switch the main breaker ON to restore utility power.

The generator will continue running to allow the engine to cool down before shutting itself OFF.

Unhook the gas meter and reinstall the port plug on the regulator.