Operator's Manual

Third Edition • Second Printing

 

 

 

 

Pre-operation Inspection

Do Not Operate Unless:

You learn and practice the principles of safe machine operation contained in this operator's manual.

1Avoid hazardous situations.

2Always perform a pre-operation inspection.

Know and understand the pre-operation inspection before going on to the next section.

3Always perform function tests prior to use.

4Inspect the workplace.

5Only use the machine as it was intended.

Fundamentals

It is the responsibility of the operator to perform a pre-operation inspection and routine maintenance.

The pre-operation inspection is a visual inspection performed by the operator prior to each work shift. The inspection is designed to discover if anything is apparently wrong with a machine before the operator performs the function tests.

The pre-operation inspection also serves to determine if routine maintenance procedures are required. Only routine maintenance items specified in this manual may be performed by the operator.

Refer to the list on the next page and check each of the items.

If damage or any unauthorized variation from factory delivered condition is discovered, the machine must be tagged and removed from service.

Repairs to the machine may only be made by a qualified service technician, according to the manufacturer's specifications. After repairs are completed, the operator must perform a pre-operation inspection again before going on to the function tests.

Scheduled maintenance inspections shall be performed by qualified service technicians, according to the manufacturer's specifications and the requirements listed in the responsibilities manual.

12

GR-12GR-15GR-20

Part No. 97779

Page 14
Image 14
Genie GR-12, GR-15, GR-20 manual Pre-operation Inspection, Fundamentals