Side cover A (Right side) Side cover A (Left side)

Installation of Indoor Unit

CONNECTION PIPE REQUIREMENT

Table 1

M o d e l

Diameter

Maximum

Maximum height

 

 

(between indoor

 

Liquid side

Gas side

length

and outdoor)

For series 522, 482, 602

9.52 mm

19.05mm

50 m

30 m

 

 

 

 

 

 

For series 282, 362

9.52 mm

15.88mm

30 m

150 m

INSTALLATION PROCEDURE

Install the room air conditioner as follows:

1. REMOVE THE INTAKE GRILL AND SIDE COVER

Air filter

(1) Remove the Air filters

(2) Remove the intake grilles

(3) Remove the Side cover A (Right and left side)

(4)This air conditioner can be set up to intake fresh air . For information about how to install for

fresh-air intake, refer to page 22 "FRESH-AIR INTAKE".

2.LOCATION OF CEILING SUSPENSION BOLTS

Intake grille

Fig. 3

30mm

Suspension bolt pitch 1530mm

INDOOR UNIT (TOP VIEW)

30mm

Dimensions

(Space Required for installation)

10mm

155mm

300mm

Suspension bolt should extend outward 30 to 50mm.

For half-concealed installation

Supension-bolt pitch should be as shown in Fig.4.

Fig. 4

40mm

Ceiling Opening:1530mm

40mm

 

 

 

 

 

 

 

Ceiling panel

Ceiling Opening:640mm

Suspension bolt should

15mm

 

extend outward 30 to 50mm.

Ceiling panel

 

14

Page 16
Image 16
Haier AC362AFEAA, AC522AFERA Install the room air conditioner as follows, Supension-bolt pitch should be as shown