ColdAir Prevention
Defrost
Notes
Whenheating is started, thefan in the indoor unit will
notbe started immediately to prevent cold air being blew
out.
During the heating, when the heat exchanger in the
outdoor unit isfrosted, the air conditioner will defrost
automatically for a few minutes. During the defrost, the
fan in theoutdoor unit does not run untilthe defrostis
completed.
When heating, the air conditioner takes a lot of heat
fromoutdoor and release the heat intothe room , therefore
theoutdoor temperature will affect the heating effect.
Adjustthe air flow direction
Seta proper room temperature
Toocold and too hot are not only harmful for
healthbut also will consume too much electricity.
Notes:After installation, please confirm that the refrigerant is not leaked.
Useof Timer
Timeset can make your room in a comfortable
temperaturewhen you wake up or come back.
Avoidthe direct sunlight and hot air flow
InstructionsOperation
6
Waita moment
Best
temperature
Operat
i
on H
i
nts
2
7
Installationof Indoor Unit
Theindoor unit shall be installed as per the indoor unit
installationdrawing:
1.Fixthe Mounting Plate and Localize the Wall-through Hole
Fixthe mountingplate as per the selected position and the piping layout (seethe installation
drawing).
Fixthe mounting plate on a smooth wall surface under the beam or beside a column. First fix the
mountingplate with asteel nail,then level it with a level meter or a drop line, then fix it with A4
50cement nails.If the expansion screws are used,first drill holes into the wall( 4.8mm), then
putthe plastic sleeve into the holes,then fix the mounting plate with4 25 screws. Measure the
positionthe wall hole with a measuring tape.
2.Drilla Hole through the Wall and Install the Piping Protective Sleeve
Drilla hole 60mmthrough the wall with the outer side slightly downward,then install the
pipingsleeve,then seal it with gypsum powder.
Installationof the Connection Pipe Clips(Left or Left-Back Connection):
Insertthe pipe clip into the fixing position of the pipe with the upper part inserted first.
Pressthe bottom of the clip until a sound Ka Ta isheard.
3.PipingLayout for Indoor Unit
Layout the connection pipe,drain pipe, and the connection wires according to the installation
positionof theindoor and outdoor units.During the layout, the drain pipe shall be placed
underneath,andthe connection wires shall be placed on the top; the drain pipe(especially indoor
orinside the unit)shall be wound up with the insulating material.

Pipe Clamp

Electrical Connection

between Indoor and

Outdoor Units

Drain Pipe

Insulating Material Pipe

Pipe Clamp

Left Connection

Tape

Low Connect oni

Right Connection

(Sectionplan of wall hole)
Thicknessof wall
Wallhole
60mm
Interside Outer side
HangingWire
HolesforFixing
DroppingWeight
Wire
A145mm
A=185mm 60mm
Find out the Level Position
DropWireHere
MountingPlate
3
Installat
i
on