SKU 35740 For technical questions, please call 1-800-444-3353. Page 7
Cord Clamp/Ground Wire Installation
Step 1: As viewed from the inside, insert one SCREW (#20) through the right side of the
CORD CLAMP (#19) and the inside of the TANK (#1). Make sure CORD CLAMP is
covering the cord of the PUMP (#6).
Step 2: On the outside of the TANK, put both ground wires (green with ring-ears) on the
SCREW. Secure using (in the following order) a LOCK WASHER (#22), WASHER
(#21), & NUT (#23).
Step 3: Leave the other side of the CORD CLAMP unattached for now.
Switch Box Wiring and Installation
Step 1: Make sure the black and white
wires from the POWER CORD
(#17) are hooked up to the bottom
terminals as shown in Figure 2.
Step 2: Connect the black and white wires
from the PUMP (#6) to the top
terminals in the same fashion as
the ones from the POWER CORD
as shown in Figure 2.
Figure 2 — Wiring Switch Box
Power Cord
#17
White
Wire
Black
Wire
Ground
(goes to tank)