AQUASTAT INSTALLATION | 23 |
|
AQUASTAT INSTALLATION
(a350My350, s350)
1.Lay the din rail on a flat surface with the flat side down. Secure one end clamp on the left side.
2.From the right side, slide the A350 control onto the din rail. Slide the control to the left until it is against the end clamp.
3.Repeat Step 2 with the Y350 power module, connecting it to the A350 control. NOTE: Be careful when fastening the
4.Repeat Step 3 with the
5.Install the other end clamp to the right side of the din rail.
6.Remove the covers on the three controls by using the four screws on each control. (A350, Y350, S350)
7.Install the terminal box to the controls by using the three chase nipples and locknuts supplied with the kit.
8.Mount the terminal box with controls to the boiler jacket or any other desired location by the four holes in the terminal box.
9.Using two
10.A350 Control: 1) Set the jumpers to the heat position. They may already be in this position. 2) Set the differential to the desired set point. 3) Terminate the wires using the common and the normally open terminals.
11.Y350 Control: 1) Terminate the power wiring using the 120 VAC terminals on the control. This will be supplied from the terminal block located in the terminal box.
12.S350 Control: 1) Set the offset to the desired set point. 2) Set the differential to the desired set point. 3) Set the jumpers to the cooling position. 4) Terminate the wiring using the common and the normally open terminals.
13.Set the A350 control to the desired water temperature.
14.After locating and installing the sensor well and sensor, wire the sensor to the A350 control. The terminals marked “sen” and “com” are located in the upper
15.Reinstall the covers on the three controls
16.NOTE: Sensor wire can be lengthened up to 50 feet with standard 22 awg
WIRE GAUGE/SHIELDED CABLE LENGTH
14 awg | 800 feet |
16 awg | 500 feet |
18 awg | 310 feet |
20 awg | 200 feet |
22 awg | 124 feet |