![](/images/new-backgrounds/1010304/1030457x1.webp)
•Install the Chase Top Flashing at the top of the chase with a 1/2 in. minimum air clearance off the top of the chase construction (Figure 8.13).
•Spacing clips can be
•
•Secure the Chase Top Flashing to the chase with at least three screws or nails per side.
•When installed, the bottom of the chimney cap must be at least 6 in. above the Chase Top Flashing.
•Secure the chase top flashing to the chase with at least three screws or nails per side.
•When installed, the bottom of the chimney cap must be at least 6 in. above the flashing (Figure 8.16).
1 1/2 in. ventilation opening around chimney pipe
1/2 in. air space established by spacing clips
1/2 in. Air Space
Storm collar must be installed 1 in. off chase top
Spacing Clips
Chase top flashing
Roof radiation shields
Required spacing clips
Figure 8.14
| Sealant |
Chase Top |
|
Collar | Screw or |
|
Note: 30 spacing clips and 20 ft
Figure 8.13
Field-Constructed Chase Top Flashing
•
•The flashing must be oversized to allow 1/2 in. air gap around all four sides.
•Include a minimum 1 in. turn down and a 1/2 in. drip edge (optional) to prevent water from seeping into the chase. Refer to Figure 8.16.
•Additional
•Spacing clips can be
•Secure the Chase Top Collar section to the
•Seal Chase Top Collar section to flashing with non- hardening waterproof sealant to ensure a weather tight connection. See Figure 8.15.
•
Screws |
|
to hold | Insect |
flashing to | |
chase top | Screen |
Additional |
|
Structural Support |
|
Roof Radiation Shields |
|
placed here |
|
Figure 8.15 |
|
1 1/2 in. ventilation |
|
opening around | Chase Top Collar |
chimney pipe |
Slope downward
Turn-down
Drip edge
Figure 8.16
Heatilator • Birmingham | 29 |