CSG GAS SUPPLY (continued)

Installation – Gas Units (continued)

CSG GAS SUPPLY (continued)

A steam burner gas valve and dry heat burner gas valve respectively are responsible for the gas supply to the indi- vidual burners. The Combi-Steamer models CSG have manual shut-off valves, that can be reached from the front without tools.

The manual shut-off valves of these units are located behind the service cover under the operator panel. To oper- ate the valves, unscrew the 2 knurled screws and pull the service cover off.

GAS LEAK TEST-CSG

After the piping and fittings have been installed, check for gas leaks. A simple checking method is to turn on the gas and brush all connections with a soap solution. If bubbles occur, it indicates escaping gas. In this event, the piping connection must be redone.

Never use a lighted match or open flame to test for gas leaks. Escaping gas could cause an explosion resulting in severe personal injury and/or property damage.

GAS PRESSURE-CS

The gas pressure should be measured when all other gas appliances in the kitchen are on high flame. The mini- mum and maximum incoming line flow pressures should be as follows:

Natural: 7-11” water column

Propane: 11” water column

During pressure testing note the following:

1.The Combi-Steamer and its individual shut-off valve must be disconnected from the gas supply piping system during any pressure testing of that system at test pressure in excess of 1/2 psig (3.45 kPa). Turn OFF main gas shut-off valve or main gas supply line.

2.The appliance must be isolated from the gas supply piping system by closing its individual manual shut-off valve during any pressure testing of the gas supply piping system at test pressure equal to or less than 1/2 psig (3.45 kPa).

3.If incoming w.c pressure is over 14” w.c. a separate regulator must be installed before the manual gas shut-off valve.