Switch Overview
Installing the Switch
1. Prepare the Installation Site
The cabling infrastructure must meet the requirements for the Switch 2510 ports. See the ProCurve Series 2510 Installation Guide on the ProCurve Web site for more information, www.procurve.com.
Installation Space Requirements
Switch | Clearance Requirements |
Orientation |
|
|
|
Front | At least 7.6 cm (3 inches) of space for the |
| cabling. |
|
|
Back | At least 3.8 cm (1 1/2 inches) of space for the power cord and switch cooling. |
|
|
Sides | At least 7.6 cm (3 inches) for cooling, except if the switch is installed in an |
| open EIA/TIA rack. |
|
|
| 2. Verify the Switch Passes Self Test |
| Before mounting the switch, verify it is working properly by plugging it into a |
| power source and confirming that it passes self test. |
|
|
N o t e | The Series 2510 Switch devices do not have a power switch. They are powered |
| on when the power cord is connected to the switch and to a power source. |
| For safety, the power outlet should be located near the switch installation. |
| The switch automatically adjusts to any voltage between |
| volts and either 50 or 60 Hz. No voltage range settings are required. |
| If your installation requires a different power cord than the one supplied with |
| the switch, be sure to use a power cord displaying the mark of the safety |
| agency that defines the regulations for power cords in your country. The mark |
| is your assurance that the power cord can be used safely with the switch. |
|
|
6