Switch Overview

Installing the Switch

1.Connect the power cord supplied with the switch to the power connector on the back of the switch, and then into a properly grounded electrical outlet

Connect power cord to the power connector

2.) Check the LEDs on the switch as described below.

Port Link LED

 

 

 

Port Mode LED

 

Switch 2510-24

 

 

 

 

 

 

 

 

 

 

 

ProCurve

* Spd mode:

Mbps,

 

flash = 100 Mbps,

on = 1000 Mbps

 

10/100Base-T Ports (1 - 24) — Ports are HP Auto MDI-X

 

 

2510-24

Link

1

Mode

3

5

7

9

11

Link 13 Mode

15

17

19

21

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

J9019A

 

 

 

 

 

 

 

 

 

 

 

 

 

Power

 

 

 

 

 

 

 

 

 

 

 

 

 

 

Fault

 

Act

 

 

 

 

 

 

 

 

 

 

 

 

 

LED

 

 

 

 

 

 

 

 

 

 

 

 

 

Mode

FDx

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

Test

* Spd

 

 

 

 

 

 

 

 

 

 

 

 

Console

Reset

Clear Link

2

Mode

4

6

8

10

12

Link 14 Mode

16

18

20

22

Power and

 

 

 

 

Test LED

 

 

 

 

 

 

 

Fault LEDs

 

 

 

 

 

 

 

 

 

 

 

 

 

 

When the switch is powered on, it performs its diagnostic self test. Self test takes approximately 50 seconds to complete.

Self Test LED Behavior:

During the self test:

Initially, all the status, LED Mode and port LEDs are on for most of the duration of the test.

Most of the LEDs go off and then may come on again during phases of the self test. For the duration of the self test, the Test LED stays on.

When the self test completes successfully:

The Power and Fan Status LEDs remain on.

The Fault and Test LEDs go off.

The port LEDs on the front of the switch go into their normal opera- tional mode:

If the ports are connected to active network devices the Link LEDs should be on.

In the default LED Mode (Act), link activity is displayed on the Port Mode LED.

7