Overview

5

About this document

5

Site assessment

5

Site requirements

6

HP Site Preparation Drawing Package

6

Site preparation

6

Early infrastructure requirements

6

Site pad

7

Other structures

7

Space requirements and clearances

8

HP POD 240a dimensions and required clearances

8

HP POD 240a weight

10

HP POD 240a and support equipment sample offload plan

10

Site space and clearance requirements

11

Additional equipment space requirements

11

Future expansions

11

Preparing for delivery and assembly

12

Shipping considerations

12

Suggested assembly installation equipment

12

Safety for assembly

12

Temporary lighting and power

13

Storage requirements

13

Assembly prerequisites

13

Environmental considerations

14

Environmental considerations

14

Cold weather

14

Areas prone to lightning or power surges

14

Seismic activity

14

Utilities

15

Proximity to utilities and drains

15

System utilities

15

Water supply

15

Drainage

16

Power

17

Required facility connections

19

Connections to central facility infrastructure

19

Network connections

19

Connection portals

19

Grounding requirements

20

Supported facility connections

23

Humidifier

23

HP POD 240a security

24