You have chilled water at your final location.

You have made provisions for properly grounding the HP POD.

System utilities

Your site location must accommodate the following utilities:

Cooling water

Electrical power ("Power" on page 5)

Drainage (on page 6)

Power

Item

Description

 

 

1

Main input power junction box

 

 

2

Chilled water return connection

 

 

3

Chilled water supply connection

 

 

4

IT cable portals

 

 

Site requirements 5

Page 5
Image 5
HP Performance Optimized Data Center (POD) 40cp manual System utilities, Power, Description