STEP 11 (See Diagram 11 & Cable Loop Diagram)

A.) Attach the 105” Lower Cable (#41) to the opening on the bottom of Leg Developer (#7). B.) Attach a Pulley (#60) to the opening. Secure it with one M10 x 2 3/8” Allen Bolt (#84), two

Pulley Bushings (#78), and one M10 Aircraft Nut (#97).

C.) Draw the Cable underneath the Pulley towards the back of the machine to the open bracket on the Right Base Frame (#1). Attach a Pulley to the Bracket. Secure it with one M10 x 1 ¾” Allen Bolt (#82), two ¾” Washers (#94), and one M10 Aircraft Nut (#97).

D.) Draw the Cable underneath the Pulley through the opening on the bottom of Right Vertical Beam (#3) to the open bracket on the Right Base Frame. Install a Pulley to the bracket with a 2 7/8” L-shaped Cable Retainer (#33).

E.) Draw the Cable around the Pulley then upward to the Flat Double Floating Pulley Brackets (#36) previously installed in Step-10. Install another Pulley.

F.) Draw the Cable around the Pulley then downward. Connect the Cable to the first open bracket on the Right Base Frame with a C-clip (#75) and a Short Chain (#74).

G.)Secure the Short Chain to the bracket with one M10 x 1” Allen Bolt (#81), two Ø ¾” Washers (#94), and one M10 Aircraft Nut (#97). After completing the entire cable installations, come back to this Short Chain and adjust the Cable tension by adjusting the length of the Chain.

21

Page 22
Image 22
Impex EVE-1500 manual See Diagram 11 & Cable Loop Diagram