STEP 8 (See Diagram 8)
A.) | Attach one end of the Leg Developer Cable (#22) to the bottom of Leg Developer |
| (#1). Secure it with one M10 x 1” Allen Bolt (#41), two ∅ ¾” Washers (#53), and |
| one M10 Aircraft Nut (#50). Do not over tighten the bolt. The cable ring needs |
| to be able to swivel on the bolt. |
B.) | Draw the Cable through the open slot to an open bracket on the Front Stabilizer |
| (#2). Attach a Large Pulley (#28) to the bracket. Secure it with one M10 x 1 ¾” |
| Allen Bolt (#42), two ∅ ¾” Washers (#53), and one M10 Aircraft Nut (#50). |
C.) | Pull the Cable towards the back of the machine. Connect the Cable to the Black, |
| Red, and Blue Cables with a |
| Disconnect the Leg Developer Cable to the Triangle Bracket when folding the |
| machine up. |
| DIAGRAM 8 |
12