Comfort PLUS Whirlpool Bath
Installation and Operation www.jacuzzi.com Page 11
English
Drop-in Installation
Before you begin your installation, please read the following:
• Observe all local and building codes.
• Determine which tools will be used during the installation.
• Additional bathtub drain parts and plumbing are commercially available at plumbing and hardware stores.
• Drain/Overow rough-in information is included with your bathtub in the installation instruction manual.
Flashing
Exploded View
1˝ x 4˝
(25mm x 101mm)
Not For Support
Mortar or
Adhesive
Suboor
Sealant
Tile
Complete the bathtub surround installation.
1 Install drain/overow according to the manufacturer’s
instructions. Refer also to the Technical
Specications Manual.
Watertight installation of the drain is the installer’s
responsibility. Drain leakage is excluded from the
Jacuzzi Luxury Bath warranty of this product.
2 Install the faucet at this time. It is recommended that
the faucet be installed by a qualied plumber.
Tile or Finished
Surface
Support Member
Level Suboor
Scrap Lumber
Motor/Pump
Proper installation of the spout plumbing and
compliance with local codes are the responsibility of
the installer. Jacuzzi Luxury Bath does not warrant
connections of water supply ttings and piping,
ll systems, or drain/overow systems. Nor is it
responsible for damage to the bathtub which may
occur during installation.
A non-ammable protective barrier must be placed
between the soldering work and the bathtub unit to
prevent damage to the bathtub.
3 Prepare the cut-out hole for the bathtub using either
the provided template or the cutout dimensions
listed in the specications table in the Technical
Specications Manual.
The template may show guides for more than one
bathtub, be certain to select the appropriate guide
lines. If under mounting is an option, be careful to
select the guide lines that apply to the installation
that you are performing.
4 Complete all deck nish work. Cover to protect from
damaging while placing the bathtub.
5 Insulation may be placed within the bathtub
surround.
Provide adequate ventilation around the motor/
pump to ensure sufcient airow and cooling.
6 Turn off power supply to dedicated GFCI protected
circuits.
7 Place a piece of scrap lumber on each of the ends
of the cutout – this will be used as a temporary
support prior to lowering the bathtub fully into the
opening.
8 Connect ex water supply lines to faucet and plug
power cords into GFCI outlets.
DO NOT use plumbing xtures or lines to lower the
unit. Allow the bathtub to rest on the supports.
9 Install the unit, inserting the motor/pump end rst,
lowering the bathtub into the opening as shown in
the illustration.
Tile or Finished
Surface
Motor/Pump
Support Member
Figure 4
Figure 5
Figure 6