- 18 -
Copyright ©2007 LG Electronics. Inc. All right reserved.
Only for training and service purposes LGE Internal Use Only
Piping Length And Elevation

• Capacity is based on standard length and maximum allowance length is on the basis of reliability.

• Oil trap should be installed every 5~7meters (16.4~23.0ft).

Pipe Size
Capacity
(Btu/h)
Suction
Evap
Max.
length
A m(ft) Additional Refrigerant
g/m(oz/ft)
Max.
Elevation
Bm(ft)
Standard
Length
m(ft)
In case more than 5m(16.4ft)
Outdoor unit
Indoor unit
A
B
A
Oil trap
Outdoor unit
Indoor unit
B
9k(C/O) 3/8" 1/4" 7.5(25) 7.5(25) 15(49) 20(0.22)
9k(H/P), 12k 1/2" 1/4" 7.5(25) 7.5(25) 15(49) 20(0.22)
18k(C/O) 1/2" 1/4" 7.5(25) 15(49) 30(98) 20(0.22)
18k(H/P), 24k 5/8" 1/4" 7.5(25) 15(49) 30(98) 30(0.32)
Installation