Mechanical Installation

1.0MECHANICAL INSTALLATION

1.1Introduction

This following section describes the requirements that must be taken into account when planning the positioning and cabling of the Liebert NXL Input/Output Cabinet.

This chapter is a guide to general procedures and practices that should be observed by the installing personnel. The particular conditions of each site will determine the applicability of such procedures.

NOTICE

All equipment not referred to in this manual is shipped with details of its own mechanical and electrical installation.

NOTICE

Three-phase input supply required.

The standard Liebert NXL UPS is suitable for connection to three-phase, four-wire (+ Earth) TN-C, TN-S, IT-G, IT-IG or, three-phase, three-wire plus ground, IT-UG.

If using with IT Power system, a 4-pole disconnect device must be included as part of building installation.

1.2Preliminary Checks

Before installing the cabinet, please carry out the following preliminary checks:

Visually examine the cabinet for transit damage, both internally and externally. Report any dam- age to the shipper immediately.

Verify that the correct equipment is being installed.

Verify that the UPS room satisfies the environmental conditions stipulated in the equipment specification, paying particular attention to the ambient temperature and air exchange system.

1.3Environmental Considerations

1.3.1UPS Room

The cabinet intended for indoor installation and should be located in a cool, dry, clean-air environ- ment.

When bottom entry is used, the conduit plate must be installed.

NOTE

The UPS is suitable for mounting on concrete or other non-combustible surface only.

1.4Positioning

The Liebert NXL Input/Output Cabinet is structurally designed to withstand lifting from the base.

! CAUTION

Risk of unit tipping over. Can cause equipment damage and personal injury.

Floor mount brackets must remain attached to the frame until the unit is being placed in its final, installed position. (The final installation will always require the unit to be bolted to another Liebert NXL product.) Failure to comply with these instructions could result in equipment damage and/or injury to personnel.