27
POWER MANAGEMENT SAMPLE #1
Objective: Save energy by turning OFF computers after
hours. Specifically, turn ON all loads except load 03 at
7:00 a.m. and then turn them OFF at 6:00 p.m. every
workday (M-F). Remain off during the weekend.
Define Parameters
Start
Loads: #1,2,4
Action: Turn ON loads
Event: Time of Day
Delay: None
Closure
Loads: #1,2,4
Action: Turn OFF loads
Event: Utility Restored
Delay: None
Step #1A: Step #1A indicates
selection of load
modules 1,2, and 4.
Step #1B: Step #1B indicates
selection of the
Day/Time feature.
Step #1C: Step #1C indicates
loads 1,2, and 4
turn On at 7:00 a.m.
Monday through
Friday with no time
delay.
Step #2: Step #2 indicates
loads 1,2 and 4 turns
OFF at 6:00 p.m.
(18:00) Monday
through Friday with
no time delay.
POWER MANAGEMENT SAMPLE #2
Objective: Extend battery time by shutting down less
critical loads. Specifically, remove load #1 one minute
after going on battery, and load #2 two minutes after going
on battery. When utility power returns, put loads #1 and
#2 back on line.
Define Parameters
Start
Loads: #1,2
Action: Turn OFF loads
Event: Utility Failed
Delay: 1&2 minutes
Closure
Loads: #1,2
Action: Turn ON loads
Event: Utility Restored
Delay: None
Step #1A:
Step #1A
indicates selection
of load module
#1.
Step#1B:
Step #1B shed
load #1 one
minute after utility
fails.
Step#2:
Step #2 sheds
load #2 two
minutes after
utility fails
Step#3:
Step #3 turns on
#1 and #2 with no
time delay when
utility power
returns.
01)LOAD #1,2,4,0
Nothing Selected
ACTION DELAY (S)
Turn OFF load 00
01)LOAD #1,2,4,0
Day Time
ACTION DELAY (S)
Turn OFF load 00
01)LOAD #1,2,4,0
M-F 7:00
ACTION DELAY (S)
Turn ON load 00
02)LOAD #1,2,4,0
M-F 18:00
ACTION DELAY (S)
Turn OFF load 00
01)LOAD #1,0,0,0
Nothing Selected
ACTION DELAY (S)
Turn OFF load 00
01)LOAD #1,0,0,0
Utility Failed
ACTION DELAY (M)
Turn OFF load 00
01)LOAD #2,0,0,0
Utility Failed
ACTION DELAY (S)
Turn OFF load 00
01)LOAD #1,2,0,0
Utility Restored
ACTION DELAY (S)
Turn ON load 00