User’s Information Manual
2Maintenance schedule (continued)
3.Fill with fresh water until the water begins to pour out of the drain.
4.Replace the cap. Press the cap onto the trap until the cap makes contact with the drain.
5.Replace the retaining screw.
The condensate trap (FIG.
boiler operation to avoid flue gas emission from the condensate drain line. Failure to fill the trap could result in severe personal injury or death.
NOTICE | Use materials approved by the authority | |
having jurisdiction. In the absence of | ||
| ||
| ||
| other authority, PVC and CPVC pipe must | |
| comply with ASTM D1785 or D2845. | |
| Cement and primer must comply with | |
| ASME D2564 or F493. For Canada use | |
| CSA or ULC certified PVC or CPVC pipe, | |
| fittings, and cement. | |
| To allow for proper drainage on large | |
NOTICE | ||
horizontal runs, a second line vent may be | ||
| ||
| required and tubing size may need to | |
| increase to 1 inch. |
Figure 2-1 Condensate Trap
PVC TEE ASSEMBLY (FACTORY SUPPLIED)
2” PVC CAP WITH
BLOCKED DRAIN SWITCH
RETAINING
SCREW
CONDENSATE FROM HEAT EXCHANGER
The condensate line must remain unobstructed, allowing free flow of condensate. If condensate is allowed to freeze in the line or if the line is obstructed in any other manner, condensate can exit from the boiler tee, resulting in potential water damage to property. Call your qualified service technician to inspect the boiler and system.
TO FLOOR
DRAIN
Condensate disposal
1. | This boiler is a high efficiency appliance that produces |
| condensate. |
2. | The rear of the boiler has a 1/2 inch (12.7 mm) PVC |
| union for connection of a 1/2 inch (12.7 mm) PVC pipe |
| (FIG. |
3. | Slope condensate tubing down and away from the |
| boiler into a drain or condensate neutralizing filter. |
| Condensate from the SYNC will be slightly acidic |
| (typically with a pH from 3 to 5). Install a neutralizing |
| filter if required by local codes. |
| A Neutralizer Kit (FIG. |
| (KIT3046). |
7.A condensate removal pump is required if the boiler is below the drain. When installing a condensate pump, select one approved for use with condensing boilers and furnaces. The pump should have an overflow switch to prevent property damage from condensate spillage. Call
your qualified service technician to inspect the boiler and system.
Figure 2-2 Condensate Disposal
1/2" (12.7 mm) PVC TEE ASSEMBLY
4. | Install the 1/2 inch (12.7 mm) PVC tee assembly |
| (shipped with the unit) as shown in FIG. |
5. | Leave the top of the 1/2 inch (12.7 mm) tee OPEN. This |
| is needed as a vacuum break. |
6. | Do not expose condensate line to freezing temperatures. |
(FACTORY SUPPLIED)
FLOOR DRAIN
OR DRAIN PAN
1/2" (12.7 mm) PVC UNION
(FACTORY SUPPLIED)
NEUTRALIZER KIT