Note: Valve must be installed

Typical piping applications (cont.):

Figure 8_Primary/Secondary Piping of a Single Boiler - 2 1/2" Valve

A = BLENDED WATER 4 of 8Manual background

B = FROM Manual backgroundManual backgroundManual background BOILER Manual background OUTLET

C = SYSTEM

RETURN

WATER

DETAIL

Note: Valve must be installed

with proper port orientation. Failure to observe port markings on the valve body prior to installing the valve could result in damage to the unit.

DETAIL

 

 

 

.

 

 

 

DIA

 

 

PIPE

 

4

APART

 

EXCEED.OF

12”

 

NOT

TO MAX

 

 

A

 

 

OR

 

 

NOTES: 1) Unit(s) high limit must be set at max.

2)Inlet and outlet connections to the boiler are shown for reference only. Actual connections may vary from those represented here. Consult the Installation and Service Manual for actual locations.

3)Unit(s) pump should operate only during firing periods.

Figure 9_Primary/Secondary Piping of Multiple Boilers - 2 1/2" Valve for each boiler

 

 

 

.

 

 

 

DIA

 

 

PIPE

 

4

APART

 

EXCEED.OF

12”

 

NOT

TO MAX

 

 

A

 

 

OR

 

 

NOTES: 1) Unit(s) high limit must be set at max.

2)Inlet and outlet connections to the boiler are shown for reference only. Actual connections may vary from those represented here. Consult the Installation and Service Manual for actual locations.

3)Unit(s) pump should operate only during firing periods.

INS7238 Rev C