This document is intended for service technicians. It contains site preparation requirements and instructions for installing a 72-inch cabinet. This document also provides instructions for transporting the cabinet to another location. These instructions assume that the reader is knowledgeable in computer system operation, maintenance, and repair.

Customer Responsibilities

The following list describes some of the items and equipment you must provide, plus the facility preparations you must complete before installing a 72-inch high rackmount cabinet:

Provide a site drawing that shows the location of the following:

Equipment currently installed at the site and the area designated for the 72-inch cabinet installation

Existing site wiring (power, signal paths, and lengths)

Equipment capable of generating electrical noise, electromagnetic interference, and heat

Provide and install the following items:

Required communications cables, wall jacks, special connectors, and associated hardware

Necessary power distribution boxes, conduits, grounds, lightning protection, and associated hardware (see "Power Requirements" on page 10)

Required auxiliary power or other equipment

Make building alterations necessary to meet wiring, environmental, and other site requirements

Make sure all site construction, wiring, or other alterations meet applicable codes, regulations, and laws (including, but not limited to, electrical, building, safety, and health)

Provide necessary storage and service areas (see "Environmental Requirements" on page 9)

Provide floor coverings and environmental systems that limit or control electricity build-up and discharge

72-Inch Cabinet Site Preparation and Installation Guide