To Start Heater WARNING

Follow the minimum fresh, outside air ventilation requirements. If proper fresh, outside air ventilation is not provided, carbon monoxide poisoning can occur. Provide proper fresh, outside air ventilation before running heater.

Provide a fresh air opening of at least 2800 square cm (3 square feet) for each 29.3 kW (100,000 BTU/Hr) rating. Provide extra fresh air if more heaters are being used.

Example: A 44 kW (150,000 BTU/Hr) heater requires one of the following:

a 4.88 m (16 foot) wide two-car garage door raised 8.59 cm (3.38 inches)

a 2.75 m (9 foot) wide single-car garage door raised 15.24 cm (6 inches)

two, 76.20 cm (30 inch) wide windows raised 28 cm (11 inches)

Manual background WARNING

Review and understand the warnings in the Safety Information Section. They are needed to safely operate this heater. Follow all local codes when using this heater.

To Start Heater

1.Follow all ventilation and safety information.

2.Fill fuel tank with kerosene or No. 1 fuel oil.

3.Attach fuel cap.

4.Plug power cord of heater into standard 230 volt/50 hertz, grounded (earthed) outlet. Use an extension cord if needed. Use only a three-prong, grounded (earthed) extension cord.

Extension Cord Wire Size Requirements

Up to 30.5 meters (100 feet) long, use 1.0 mm2 (16 AWG) conductor

30.6 to 61 meters (101 to 200 feet) long, use 1.5 mm2 (14 AWG) conductor

Heater will start when power cord is plugged into outlet. If not, push in flame- out control reset button (see Figure 4).

Flame-Out Manual backgroundManual background

Control

Reset Button

(Fan Guard

Removed)

Figure 4 - Flame-Out Control Reset Button

Continued

7

101487

Page 7
Image 7
Master Lock BH150CE owner manual Ventilation Operation, To Start Heater