Miele Service Pack: Qualification of cleaning systems
In the pharmaceutical,
Qualification involves the following: Design Qualification (DQ), Installation Qualification (IQ), Operation Qualification (OQ), Perfor- mance Qualification (PQ) and, in some cases, process validation. In all cases, re- sponsibility for implementing the necessary measures lies with the equipment operator. Miele’s
Installation Qualification (IQ)
The objective of Installation Qualification is to verify that the cleaning system and its installation comply with the operator’s and manufacturer’s requirements. During the IQ inspection, Miele service engineers docu- ment, check and assess the following: Compliance of shipment with original order, unit configuration and condition, in- stallation and connection to
Implementation
Before IQ/OQ can be performed by Miele’s
Operation Qualification (OQ)
The objective of Operation Qualification is to furnish proof that the cleaning system meets the requirements of the operator and equipment manufacturer when in- stalled and connected. Operation Qualifi- cation documentation, inspections and evaluation cover functions with a relevance to safety and operation,
Training of service engineers
Miele’s own service engineers are given training covering all aspects of machine technology (installation, programming, re- pair and maintenance) in regular refresher courses. This is complemented by spe- cialised training on the qualification of Miele cleaning systems used in industrial and laboratory operations. Theory and practice are not confined to
Training of operatives and the documenta- tion of such measures is also carried out during Operation Qualification. This consti- tutes a comprehensive package compris- ing IQ/OQ paperwork, the services of high- ly skilled and qualified service engineers and the use of calibrated, certified test apparatus.