FIREPLACE FRAMING
Firebox framing can be built before or after the appliance is set in place. Construct firebox framing following Figures 9 through 12 and the chart below for your specific installation requirements. See Figure 1 on Page 6 for firebox dimensions. The framing headers may rest on the top of the firebox standoffs.
The firebox may be installed directly on a combustible floor or raised on a platform of an appropriate height. When the firebox is installed directly on carpeting, tile, or other combustible material, other than wood flooring, the firebox shall be installed on a metal or wood panel extending the full width and depth of the enclosure.
WARNING
Do not fill spaces around firebox with insulation or other materials. This could cause a fire.
D
F
G
C
A
E
Figure 9 - Corner Installation
Combustibles may not come any closer to the top of the enclosure than the standoffs will allow.
| MCUF36D | MCUF42D |
A | 411/4" | 471/4" |
B | 373/4" | 373/4" |
C | 32" | 38" |
D | 163/8" | 193/8" |
E | 687/8" | 747/8" |
F | 341/2" | 371/2" |
G | 173/4" | 173/4" |
H | 483/4" | 53" |