Installing the server and connecting the peripheral devices Standard 1.01
48 CallPilot
Installing the server
Introduction
Before you install the 703t server, ensure that the chosen location meets the
requirements identified on the “Site inspection checklist” provided in
CallPilot Installation and Configuration Part1: Installation and
Maintenance Overview (555-7101-210).

To install the server

1Place the 703t server in its chosen location.
Note: The server must be placed within 20 m (60 feet) of the Meridian 1
switch or Succession 1000 system.
Note: The DS30X cable that connects MPB96 boards to MGate cards is
20 m (60 feet) long. This allows the server to be placed in a different
room from the Meridian 1 switch or Succession1000 system.
2Connect peripheral devices as described in the remainder of this
chapter.