A typical installation and connection routine for the L560RC 2/3Kw searchlight is as follows:

Referring to wiring diagram C22978, a supply is fed to the control panel, which then provides a common feed to the motor gearbox and the searchlight.

Cables required to be connected by the customer: -

4 core 1.5mm2 cable from the Motor Gearbox to the Control Panel. 12 core 0.5mm2 cable from the Motor Gearbox to the Control Panel.

(Customer may need to provide a suitable junction box to extend these two cables – 3 metres supplied). The Mains cable to the Control Panel to be supplied by the customer.

The searchlight head is pre-wired along with the connecting cable to the motor gearbox.