Installation and commissioning
8.03 | Commissioning the machine |
|
|
| ● Check machine and in particular |
|
| electric lines for damage before first |
|
| commissioning. |
| 1 | ● Remove pin 1 of the oil reservoir 2 |
|
| (Fig. 8 - 08). |
|
| The pin serves only to protect |
|
| the machine from damage |
|
| during transport and must not |
|
| be used when sewing. |
|
| ● Clean the machine thoroughly and oil it |
|
| (see chapter 10 Care and maintenance). |
|
| ● Have skilled personnel check if the ma- |
|
| chine can be operated with the available |
|
| mains voltage. |
Fig. 8 - 08
Do not operate the machine if there is any discrepancy.
The machine may only be connected to an earthed socket!
Have home position of the machine drive verifi ed by certifi ed technicians before first commissioning! Have settings carried out my technicians where required (see chapter 8.05)
8.04 Switching the machine on/off
●Switch the machine on (see Chapter 7.01, On/off switch).
22