TURBOPOWER 99 WATER HEATER
3.Place the appliance on a level,
4.Do not install on carpet or other combustible floor coverings.
5.Installation over a combustible floor: Units installed over a combustible floor MUST be provided with a base of hollow clay tile or concrete blocks from 8" to 12" thick and extending 24" beyond the sides. Place the blocks in line so that the holes line up horizontally to provide a clear passage through the blocks. Install 1/2” fireproof millboard with a
4.5Installation
WARNING: Use industry standard safe rigging methods when attempting to lift or move this product. Failure to follow these instructions could result in property damage, serious injury or death. One common method includes the use of straps and spreader bars, lifting from the water heater base skid assembly.
1.Check the data decal on the appliance. Be sure the electrical, water, oil, or gas supply is adequate for the installation.
2.Carefully remove all shipping supports and bracing.
3.Use only
4.Install
5.Insulate hot water and return circulation lines. Insulate cold water supply lines if subject to freezing during shutdown periods. IMPORTANT: Do not use the plumbing connected to the appliance as a ground for welding or any other purpose.
6.Pipe the drain valve to a suitable open drain.
4.6Service Clearances
Allow sufficient space to provide adequate clearances on all sides for service and inspection. Recommended clearance is 24” at the top and front, 18” at left and right sides of the appliance. Optional equipment may increase the clearance requirements. Allow sufficient space for installing and servicing connections such as water, gas, vent, combustion air, electrical, pump and other auxiliary equipment.
4.7Clearances to Combustible Surfaces
The appliance must not be installed on a combustible floor, on carpet, on other combustible floor coverings or on a
7 |