Raypak 122-322 manual Post Start-Upcheck, Operation, Follow-Up, Operating Instructions

Models: 122-322

1 44
Download 44 pages 22.92 Kb
Page 38
Image 38
Follow-Up

Follow-Up

Safety checks must be recorded as performed.

Turn unit on.

After main burner ignition:

Check Manometer for proper reading.

Cycle unit several times and recheck readings

Re-analyze with unit running record or print results.

Remove all Manometers and replace hose, remove jumper, replace all gas pressure caps.

Check for gas leaks one more time.

POST START-UP CHECK

Check off steps as completed:

1.Heater and heat distribution units or storage tank filled with water?

2.Automatic air vent, if used, open two full turns dur- ing venting procedure?

3.Air purged from system?

4.Air purged from gas piping? Piping checked for leaks?

5.Followed start-up procedure for proper start-up?

6.Is burner flame visible?

7.Test safety controls: If heater is equipped with a low water cut-off or additional safety controls, test for operation as outlined by manufacturer. Burner should be operating and should go off when con- trols are tested. When safety devices are restored, burners should reignite after pre-purge time delay.

8.Test limit control: While burner is operating, move indicator on high limit control below actual heater water temperature. Burner should go off while blower and circulator continue to operate. Raise setting on limit control above heater water temper- ature and burner should reignite after pre-purge time delay.

9.Test ignition system safety device:

·Turn on manual gas valve. Turn power on.

·Set thermostat to call for heat.

·When the unit is in operation. Disconnect combus- tion air blower pressure switch, burner should go

off immediately.

·Wait 5 minutes.

·Reconnect combustion air pressure switch, burner should reignite after pre-purge time delay.

10.To restart system, follow lighting instructions in the Operation section.

11.High limit control set to design temperature requirements of system? For multiple zones: flow adjusted as required in each zone?

12.Heater cycled with thermostat? Raise to highest setting and verify heater goes through normal start-up cycle. Reduce to lowest setting and verify heater goes off.

13.Observed several operating cycles for proper operation?

14.Set room thermostat or tankstat to desired temper- ature?

15.Reviewed all instructions shipped with this heater with owner or maintenance person, returned to envelope and given to owner or placed in pocket inside front panel on heater?

OPERATION

Operating Instructions

Lighting Instructions

1.STOP! Read the safety information first.

2.Set the thermostat to the lowest setting.

3.Turn off all electric power to the appliance.

4.This appliance is equipped with an ignition device which automatically lights the burner. Do Not try to light the burner by hand.

5.Remove upper front panel.

6.Turn on main manual gas valve.

7.Wait five (5) minutes to clear out any gas. Then smell for gas, especially near the floor. If you then smell gas. STOP! Follow the steps in the safety information on the front cover. If you do not smell gas, go to next step.

38

Page 38
Image 38