SMA Technol ogie AG Hand-over to the Operator
Installation Guide SMC50A_60A-IEN073320 Page 57
9 Hand-over to the Operator
After installing the Sunny Mini Central successfully, hand the system over to the
operator. To do so, please use the following check list.
No. Checkpoint Control
What the operator should know:
1operating principles of the PV system
2switching the PV system on and off
3meaning of the LEDs and display messages
4maintenance and cleaning (handle covers, LEDs, display,...)
5handling of additional communication components
6contact partner in case of a failure
7keep the documents to hand close to the Sunny Mini Central
The following documents are handed over to the operator:
1operating manual of the Sunny Mini Central
2installation guide of the Sunny Mini Central
3declaration of conformity of the Sunny Mini Central
4if necessary, all manuals for additional components (interfaces,
data logger, etc.)
5data sheet for the solar modules used
6diagram of the layout of the solar modules and their wiring
7current circuit diagram of the unit
8the complete registration and commissioning documents of the
local energy supply company