/ Receiving and Inspection /
The heater package is shipped directly from the vendor.
1.Check all parts for any damage in transit. The carrier is responsible for the condition of the heater package upon arrival. If damage is appar- ent, note the freight bill accordingly. This will support your claim with the freight carrier.
2.Check the nameplate on the enclosure and verify that the heaters and the control panel are rated for the correct voltage.
3.Check the watt rating on each element and verify the sum of all elements is equal to the KW rating as ordered.
4.The control panel is nameplated for the maximum amperage that the
panel can safely control and may be equal to or greater than the actual amperage required for your heater package. See Installation Instructions
on page 5 to calculate amperage required.
3