1. INSTALL DUCTWORK

Plan where and how the ductwork will be installed.

Install proper-sized ductwork, elbow(s) and roof or wall cap for the type of blower you are installing. If using 6’’ (150 mm) round ducts, use a transition. Use 2’’ (50 mm) metal foil duct tape to seal joints.

Roof cap

3¼” x 10” duct

Wall cap

Hood

Roof cap

6” round duct

3¼” x 10” to 6” round transition

Wall cap

Hood

HH0011A

HH0014A

2. MEASURE THE INSTALLATION

Dimensions for the most common installations are shown below.

We recommend to install the hood at a minimum of 20” (508 mm) from an electric range and at 24” (610 mm) from a gas range.

For optimal performance, the hood should not be installed more than 30” (762 mm) from cooktop.

Cabinets

Hood

20” minimum clearance (24” for gas)

Standard 36” height cooktop

Cabinets

Hood

30” maximum clearance

Standard 36” height cooktop

HH0013A

HH0012A