GLASS CLEANING
It will be necessary to clean the glass periodically. During
Clean glass after first two weeks of operation.
CERAMIC REFRACTORY INSTALLATION
DVRS3 (Fig. 66)
Rear refractory is already installed from factory.
1 . Unpack ceramic refractory from its carton. HANDLE REFRACTORY CAREFULLY.
2.Place bottom refractory manifold side onto fireplace floor and slide under rear refractory.
3.Place bottom sides onto fireplace floor.
4.Place bottom end refractory onto fireplace floor.
REAR
REFRACTORY
BOTTOM
REFRACTORY
MANIFOLD SIDE
BOTTOM SIDE
REFRACTORY
BOTTOM SIDE
REFRACTORY
BOTTOM END | Fig. 66 | |
REFRACTORY | ||
|
DVRSL/DVRSR Fig. 67
Rear and side refractory are already installed from factory.
1 . Unpack ceramic refractory from its carton. HANDLE REFRACTORY CAREFULLY.
2.Place bottom rear refractory manifold side onto fire- place floor and slide under rear refractory.
3.Place bottom side refractory onto fireplace floor.
4.Place bottom end refractory onto fireplace floor.
REAR
SIDEREFRACTORY REFRACTORY
BOTTOM
REFRACTORY
MANIFOLD SIDE
BOTTOM END | BOTTOM SIDE |
REFRACTORY | |
REFRACTORY | Fig. 67 |
- 28 -