7.From the front, install four
8.Lift the shelf up and slide the shelf into position over the screw heads (Fig. 11).
9.Tighten the four screws to secure the shelf.
Fig. 10 | Fig. 11 |
LEVELING
Check the leveling of the range. Place a carpenter’s level inside the oven cavity across the oven rack(s). Level
To adjust the leveling, tilt the range to one side and, using channel locks, unscrew the adjustable leg insert as required. Repeat this procedure as necessary for each leg.
Casters for this range are of the
GAS CONNECTIONS
CAUTION: All gas supply connections and any pipe joint compound used must be resistant to the action of propane gases.
Each range is
Connect gas supply. Make sure the pipes are clean and free of obstructions.
Codes require that a gas shutoff valve be installed in the gas line ahead of the range.
Standard ranges are equipped with fixed burner orifices which coincide with installation elevation.
Install the gas pressure regulator.
Before installing, ensure that regulator supplied agrees with rating plate gas supply.
— 14 —