STEP 1 UNPACKING DOORS

Before removing the door from any packaging, inspect the packaging for visible signs of damage. If damage is noted, file a freight claim with the freight company immediately. Remove the door from the packaging.

IMPORTANT!

Do not cut tape that holds door in a roll. You will be told in STEP #7 when to cut the tape.

No guarantee will be given by Wayne-Dalton if the door is not installed as

instructed. Please review all instructions thoroughly before starting installation. For proper operation, follow these instructions step by step.

NOTE:

Right and Left Hand is determined by facing the door opening, on the coil side.

STEP 2 CHECKING THE DOOR OPENING

Verify that dimensions W and H (see below) match those recorded on the door packing slip. Consult the factory if the actual opening width is greater than that shown on the packing slip by more than 1-1/2 inches. Check to make certain that the door opening is square and plum and that the floor is level. Check to be certain there is sufficient clearance from the opening to the ceiling and the sidewalls (see Required Clearances below).

OPENING HEIGHT

HEADROOM (A)

 

SIDE ROOM (B)

 

 

 

 

 

 

 

 

UP TO 6’8” HIGH

13”

 

4”

 

 

 

 

FROM 6’8-1/4” TO 8’ HIGH

14”

 

4”

 

 

 

 

OVER 8’ HIGH

16”

 

4”

 

 

 

 

REQUIRED CLEARANCES - MINIMUM INDICATED