Step 7: Performing Checks Prior to Initial Start-UpBefore testing your installation, ensure these conditions are met:
❐Chassis and AC grounds are properly installed.
❐AC input connections and AC output connections are wired correctly
on the terminal block and not reversed.
❐Positive (+) battery cable is connected to the positive (+) battery
terminal through the DC fuse and disconnect switch or DC circuit
breaker.
❐Negative (–) battery cable is connected to the negative (–) battery
terminal.
❐Battery voltage is within the proper range for this unit
(10–16 volts DC).
❐DC disconnect switch or breaker is turned off.
❐AC input and output breakers are turned off.
❐All connections are tight.