CEILING INSTALLATION
Hanging arm
Chart 7
1.Remove the side board and the grille. (Refer to Chart 8)
(For models 48000 and 60000 Btu/h, do not remove the grille.)
Side board
Grille
Chart 8
2.Locate the hanging arm on the hanging screw bolt. (Refer to Chart 9) Prepare the mounting bolts on the unit. (Refer to Chart 10)
25mm |
| 8•• 13mm |
|
| |
20•• | Screw nut |
|
Washer |
| |
| Hanging |
|
| screw bolt | Mounting bolt (max. 40 mm) |
|
| |
| Hanging arm |
|
| Chart 9 | Chart 10 |
3.Hang the unit on the hanging arm by sliding backward. Securely tighten the mounting bolts on both sides. (Refer to Chart 9)
Hanging screw bolt
Hanging arm
Mounting bolt
D. Connecting point of refrigerant pipe
| (D. gas side) |
| E. Connecting point of refrigerant pipe |
>20mm | (E. Liquid side) |
|
Drain point
Chart 11
ATTENTION: The figures above are based on model with 18000 Btu/h as rated capacity, which may differ from the unit you purchased.
The dimension of the unit
Capacity | A | B | C | D | E | F | G | H | |
(Btu/h) | |||||||||
|
|
|
|
|
|
|
| ||
990 | 660 | 206 | 505 | 506 | 907 | 200 | 203 | ||
36000 Btu/h | 1280 | 660 | 206 | 795 | 506 | 1195 | 200 | 203 | |
1670 | 680 | 244 | 1070 | 450 | 1542 | 200 | 240 |
•Note: The dimension of 12000 Btu/h and 24000 Btu/h are the same The dimension of 48000 Btu/h and 60000 Btu/h are the same
Outdoor unit
| ||||||
285 | 750 |
| 845 | 313 | 895 | 300 |
|
| 301.5 |
|
|
|
|
| 590 | 695 |
| 860 |
|
|
|
| 351.2 |
|
|
|
|
|
| 135 |
| 163 | 590 |
|
| 62 | 141.5 | 560.1 |
| ||
|
| 235 |
|
|
| |
|
|
|
|
|
| |
315 | 290 | 335 | 125 | 330 |
|
|
|
|
|
| |||||||
| 990 | 336.4 | 400 |
|
| 940 |
|
|
|
|
960 |
|
|
|
|
|
|
|
|
|
|
|
|
|
| 1245 |
|
|
|
|
|
|
181.4 | 624 |
|
|
|
|
|
|
|
|
|
360 |
|
|
|
|
|
|
|
|
|
|
|
|
|
| 360 |
|
|
|
|
|
|
❥✱DC Inverter |
|
|
| 650 |
|
|
|
| ||
|
|
| MODEL | A | B | C | D | E | H REMARK | |
|
| H | 18 | 840 | 550 | 335 | 360 | 310 | 677 |
|
|
|
| 24 | 894 | 590 | 333 | 355 | 302 | 860 | |
|
|
| 36 | 990 | 624 | 366 | 396 | 340 | 960 | |
|
|
|
| |||||||
|
| A | 48 | 940 | 600 | 376 | 400 | 340 | 1245 |
|
|
| B |
|
|
|
|
|
|
|
|
D C |
| E |
|
|
|
|
|
|
|
|
INSTALLATION IN THE FOLLOWING PLACES
MAY RESULT IN TROUBLE
Installation of the indoor unit in direct sun light. | Installation in the unit in wrong direction. |
Installation of outdoor units too close or, | Installation of the indoor unit in a place where |
blowing discharged air into each other. | there is an obstacle near the air inlet or outlet. |
| > 30 cm |
Installation of the outdoor unit in a place | Installation of the indoor unit at too high > 30 cm |
exposed regularly to a strong wind. | a position. |
INDOOR UNIT INSTALLATION
Installing Ø10 hanging screw bolts. (4 bolts)
•Please refer to the following figure for the distance measurement between the screw bolts.
•Please install with Ø10 hanging screw bolts.
•The handling to the ceiling varies from the constructions, consult the construction personnels for the specific procedures.
1.The size of the ceiling to be handled ... ... do keep the ceiling flat. Consolidate the roof beam for possible vibration.
2.Cut off the roof beam.
3.Strengthen the place cut off, and consolidate the roof beam.
•Carry out the pipe and line operation in the ceiling after finishing the installation of the main body. While choosing where to start the operation, determine the direction of the pipes to be drawn out. Especially in case there is a ceiling, position the refrigerant pipes, drain pipes, indoor & outdoor lines to the connection places before hanging up the machine.
•The installation of hanging screw bolts.
530 110