Bosch | Supplier Logistics Manual, Release. 3.0 |
confirmed the stock balance quoted. Quantity discrepancies shall be eliminated by SUPPLIER with the assistance of the responsible BOSCH packaging planner and/or the EDL.
In this context and in the case of complaints (for example caused by quantity differences, waste, damage) the supplier has to provide photos, a short description with reference to the delivery note number to the responsible Bosch Returnable Packaging Planer.
If the complaint is already visible after transfer from the service provider the driver of the forwarder has to sign off on that complaint at the shipping note. This voucher must be forwarded to the Bosch packaging planner as well. Otherwise the complaint will not be accepted. The following procedure has to be agreed with the Bosch packaging planner on a case by case basis.
Euro pallets and Euro box pallets are subject to the standard local and industry specific regulations. In case of doubt, the regulations of the European Pallet Association (Internet:
Quantity discrepancies or shrinkage shall be compensated immediately at the current replacement value by the PARTY deemed responsible.
2.2.3 Supply of empties
If SUPPLIER fails to request or procure packaging at the appropriate time, it shall bear the additional costs that may be incurred (such as shipping or repacking costs).
a) Poolable Euro pallets / Euro box pallets
Euro pallets and Euro box pallets are subject to the standard local and
b)
SUPPLIER shall request the required empties promptly in written form, allowing for factors such as transportation times. The
2.2.4 Storage, Repair and Replacement Procurement
The supplier is responsible for a proper storage (weather protected) of the returnables after transfer of the returnables from the Bosch forwarder. The returnables have to be stored in that way that contamination before, during and after the production process can be avoided. If contamination occurs during this period the SUPPLIER has to clean the returnables provided by BOSCH at its own expense.
BOSCH shall repair or scrap damaged returnables as appropriate. BOSCH shall charge 50% of the repair or current replacement value to SUPPLIER – if there is no other bilateral agreement between BOSCH and SUPPLIER. Packing materials used by more than one supplier at any one time shall be
Robert Bosch GmbH, CP/LOG, 07.05.2007 | Page 19(35) |