Bosch | Supplier Logistics Manual, Release. 3.0 |
5.Check the possibility of partial delivery
6.Premium freight capabilities and timing
7.Escalation of the problem inside its company
If no mutually agreed solution can be found, involvement from the highest levels within SUPPLIER’s organization will be required.
Liability of SUPPLIER due to late delivery is regulated by the relevant delivery contract.
1.3.3Production and Material Release
SUPPLIER is obliged to deliver ordered products and required associated materials to the receiving BOSCH plant.
Production releases are legally binding purchase orders of finished goods. However, regarding delivery dates the last updated delivery
Material releases are the basis for BOSCH’s obligation to reimburse respective materials purchased by SUPPLIER, if any. Production and material releases relate to dates of receipt by BOSCH.
Periods for production and material releases are defined in general in the relevant supply contract. If the agreed releases are verifiably inadequate to maintain delivery capability, SUPPLIER can apply for an extension for material release or request additional forecast data from his BOSCH contact in individual cases. Requirements beyond those periods represent
If BOSCH cancels delivery
If BOSCH cancels delivery
1.3.4Start-Up and Phase-Out Management
During
Capacity planning must be coordinated between BOSCH and SUPPLIER in time.
1.3.5Order Processing Using the VMI Process
The processes and agreements described in sections 1.3.1 to 1.3.4 are to be applied analogously with VMI (DCM). Deviations are pointed out in the following.
Robert Bosch GmbH, CP/LOG, 07.05.2007 | Page 11(35) |