Performing a Readiness Check
The activity log reports the overall results of the readiness check as well as the results for each individual test. Table
Table 4-1. Activity Log Entries
Icon | Text Color | Severity | Description |
|
|
|
|
| Green | Success | Task completed without error |
|
|
|
|
| Black | Pending | Task is in progress |
|
|
|
|
| Black | Information | Task information, no action necessary |
|
|
|
|
| Black | Warning | A problem that should be addressed, but will not |
|
|
| block an upgrade |
|
|
|
|
| Red | Error | A problem that must be corrected before continuing |
|
|
| with upgrade |
|
|
|
|
The status bar at the bottom of the window indicates one of the following states for the current operation:
• Busy
A readiness check is in progress. Allow time for the task to complete.
• Ready
The system meets the prerequisites for the Active Upgrade process. You can proceed with the upgrade process by splitting the system.
• Broken
One or more components in the system does not meet the prerequisites for the Active Upgrade process. You must resolve the problem before you can continue with the upgrade.
(For more information about interpreting Active Upgrade status, see “Viewing Active Upgrade Process Status” on page
If the check is successful, you can click Split to proceed with splitting the system. See “Splitting the System”.
If one of the readiness tests fails, you must resolve the problem, then click Retry to run the readiness test again. When the problem is resolved, you can click Split to proceed with splitting the system.