ATEN Technology ACS-1216AL, ACS-1208AL user manual Installation

Page 22

Installation

To set up a daisy chained installation, do the following:

1.Make sure that power to all the devices you will be connecting up has been turned off.

2.Use a daisy chain cable set (described in the Cables section, p.

1-4), to connect the Chain Out port of the parent unit to the Chain In port of the child unit (First Station Out to Second Station In, Second Station Out to Third Station In, etc.).

3.Use KVM cable sets (described in the Cables section, p. 1-4), to connect any available CPU Port to the Keyboard, Video and Mouse ports of the computers you are installing.

4.Repeat the above steps for any additional Master View units you wish to add to the chain.

5.Power up the installation according to the following procedure:

a)Plug in the power adapter for the First Station.

Wait a few seconds for the unit to ascertain its Station ID.

b)Plug in the power adapters for each Station on the installation in turn (Second Station, then Third Station, etc.).

Each ACS-1208A / ACS-1216A has a LED display on its front panel to indicate its Station ID (the Station ID for the First Stage unit is 01, the ID for the Second Stage unit is 02, the ID for the Third Stage unit is 03, etc.).

In each case, wait for the Station ID to be ascertained and displayed on the Station ID LED before plugging in the next Station.

c)After all the Stations are up, power on the computers.

2-3

2003-01-27

Image 22
Contents ACS-1208AL ACS-1216AL For additional information 2003-01-27 Packing List Table of Contents Appendix B, Module Removal Firmware Upgrade UtilityAppendix A, Technical Information Appendix C, Rack MountingAbout This Manual OverviewKey information Viii 2003-01-27 Introduction Overview2003-01-27 Features Hardware Requirements Function CS Part Number2L-1700 / 2L-1701 2L-5201P / 5202P / 5203P ACS-1208AL / ACS1216AL Front View CoverKeyboard Power LED ACS-1208AL / ACS-1216AL Rear View Cable Tie SlotFirmware Upgrade Port LCD OSD Configuration LCD OSDSingle Stage Installation InstallationBefore you Begin Daisy Chaining Installation ACS-1216AL Switching Station Positions Hot PluggingPort ID Numbering Powering Off and Restarting Port Selection2003-01-27 Invoking Hotkey Mode Hotkey Port AccessHotkey Operation Selecting the Active Port Press EnterSetting the Scan Interval Invoking Auto Scan Hotkey Operation Control Hotkey SummaryOSD Operation OSD OperationWEB Server Heading Explanation OSD NavigationOSD Main Screen Headings SN-PNOSD Functions F1 GotoF2 List Choice MeaningF3 SET Setting FunctionScroll Lock Scroll Lock or Ctrl Ctrl Quick View + Powered on Only those Ports which F4 ADM + / . and Space View Ports AccessibleSET Quick PortsStation IDS ResetUpgrade FirmwareF5 SKP F6 BRC F7 Scan F8 Lout 2003-01-27 Firmware Upgrade Utility IntroductionBegin Performing the Upgrade Upgrade2003-01-27 Firmware Upgrade Utility Upgrade Failed Firmware Upgrade Recovery 2003-01-27 ACS-1208AL Technical InformationACS-1208AL / ACS-1216AL Connection Tables MVsSetting Default OSD Factory Default SettingsACS-1216AL Specifications Function ACS-1208AL ACS-1216ALClear Login Information Limited Warranty TroubleshootingSymptom Possible Cause Action 2003-01-27 Module Removal Removing the KVM ModuleRemoving the Keyboard and Touchpad Module Removal 2003-01-27 Rack Mounting Standard Rack MountingOptional Rack Mounting Rack Mounting 2003-01-27 Index ACS-1216LLCD