Wiring and Connecting the UPS

5000 VA XLI MODELS ONLY: HARDWIRING INSTRUCTIONS

Wiring must be performed by a qualified electrician.

Install a high magnetic 30/32 A utility circuit breaker.

Adhere to all national and local electrical codes.

Use #10 AWG gauge (5 mm2) wire.

1.Switch the utility circuit breaker OFF.

2.Remove the input access panel.

3.Remove circular knockout.

4.Run #10 AWG gauge (5 mm2) wire through the access panel, and connect the wires to the terminal block (Green: Ground, Brown: Hot, Blue: Neutral). Use an appropriate strain relief (not included).

5.Switch the utility circuit breaker ON.

6.Check line voltages.

7.Replace the access panel.

3

Image 3
Contents Smart-UPSRT Unpacking SpecificationsInstallation IntroductionWiring and Connecting the UPS Connecting the Battery Modules and Attaching the Front Bezel Normal bypass Avoid using extension cords Operation Troubleshooting in this manualDoes not affect the voltage display ON, OFF User Configurable ItemsXLJ models Connecting the EPO Emergency Power OFF Option Terminal Mode to Configure UPS Parameters VA models Page Maintenance and Transport Replacing the Battery ModuleDisconnecting the Battery for Transport TROUBLESHOOTING, SERVICE, and Warranty Information Bypass LED Illuminates Limited Warranty ServiceRadio Frequency Warnings APC Worldwide Customer Support