Sun Microsystems 2000E installation manual Bottom Top Power Supply

Page 41

2

 

Sense cable to top power supply

Sense cable to bottom power supply

Sense cable to backplane

Power supply adapter board

LEDs (2 each)

Bottom

Top

Power Supply

Power Supply

Figure 2-23Power Supply Adapter Board LEDs

Table 2-1LED Status Indicators

Location

LED

Condition

Front panel

Left LED

On — DC power supply is receiving AC current.

 

(green)

Off — There is no DC power.

 

Middle LED

On — (first 60 seconds) Self tests are running.

 

(yellow)

Off — (after self tests end) No hardware failures.

 

 

On — (after self tests end) Hardware failure was detected.

 

Right LED

Off — (first 60 seconds) Self tests are running.

 

(green)

On — (after self tests end) System is running.

 

 

Off — (after self tests end) System cannot run; repair is needed.

 

 

 

All system boards

Lower 8 LEDs

During POST, LEDs cycle on and off in irregular pattern.

Master system board only

Lower 8 LEDs

After POST, LEDs display cyclic pattern.

All slave system boards

Lower 8 LEDs

After POST, LEDs display solid pattern until boot is ended, then LEDs

 

 

display same cycling pattern as master board. After boot ends, for boards

 

 

without SPARC modules, LEDs continue to display solid pattern. After

 

 

boot ends, LEDs on failed boards should be OFF.

Power supply adapter

Left LED

On — bottom power supply failed, or the circuit breaker (breaker box)

board (redundant-

 

tripped.

capable chassis only)

Right LED

Off — top power supply fail, or the circuit breaker (breaker box) tripped.

 

 

 

Power Supply Installation

2-25

Image 41
Contents SPARCcenter 2000E Power Supply Installation Manual Trademarks Contents SPARCserver 2000E Power Supply Installation Manual-April Figures SPARCserver 2000E Power Supply Installation Manual-April Tables Viii How This Book Is Organized Power Supply Installation, explains how to performPreface Application Title Part Number Related DocumentsWhat Typographic Changes Mean Shell Prompts in Command ExamplesXii Before You Start Safety PrecautionsProblem Precaution SymbolsOFF Tools Required Power Supply Installation Operating System Open Boot PromPowering Down the System OnDiagnostics Secure Standby Identifying a Redundant-Capable Cabinet AccessInstalling the Bottom Power Supply Preparation Installing the SupplyDisconnect the top power supply power cord 4Disconnecting the Top Power Supply Power Cord Remove the power supply cage cover panelRemove the AC Distribution Unit Remove the Breaker Box Filter Cable Power Supply Physical InstallationPower supply cage Screws 6 places Tighten all nuts and screws installed in and Step Main Bus Bar InstallationInstall the bottom cover panel 12Installing the Main Bus Bar Power Harness Installation+12V +12V Return Power harness Part Plug in the filter cable Cabling16Replacing the Power Breaker Box Place the breaker box against power supply cage17Connecting the Power Cords Plug it into J1 near the top of the supply Power Supply Sense Cable19Replacing the Power Supply Compartment EMI Panel Restore the SystemRestarting the System Turn the key switch to Power-on position. See FigureRemote Local Watch the terminal screen for any Post error messages 21System Reset Switch Reading Boot MessagesDC power green Fault yellow System running green Bottom Top Power Supply SPARCserver 2000E Power Supply Installation Manual-April Opening the Hinged Door AccessRemoval Procedures 1Opening the Hinged Door Removing the Vented Front Panels2Removing the Vented Front Panels Removing the Side Panels3Removing the Side Panels Removing the EMI Shield4Removing the EMI Shield Rear Screen PanelEMI Panel Closing the SystemSide Panels Vented Front PanelSPARCserver 2000E Power Supply Installation Manual-April Revision History SPARCserver 2000E Power Supply Installation Manual-April Reader Comments Business Reply Mail